Efficient Inversion and Prediction Method for Construction Response of Metro Cross Passages Accounting for Stratigraphic Variability
Author:
Affiliation:

1.State Key Laboratory of Intelligent Construction and Healthy Operation and Maintenance of Deep Underground Engineering,China University of Mining and Technology;2.School of Mechanics and Civil Engineering, China University of Mining and Technology;3.PipeChina Shandong Branch;4.Guangzhou Metro Design and Research Institute Co., Ltd.

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    地铁联络通道机械法施工工期短、风险高,实现施工响应的快速预测十分必要;由于施工影响范围大、地层参数可靠度低,基于实测数据的考虑地层变异性的三维有限元反演成为必需,但传统全耦合反演面临算力瓶颈。为此,提出融合地层变异性建模与代理模型的施工响应高效反演预测方法框架。以宁波地铁3号线联络通道为例,首先基于三维马尔可夫随机场建立稀疏钻孔数据下的地层变异模型,以解耦蒙特卡洛模拟带来的计算负担;随后经基于三维有限元模型的敏感性分析筛选各施工步及地层的关键土体力学参数,并批量计算获得各施工步数据库,进而分别基于极端梯度提升树与支持向量回归构建代理模型替代耗时的有限元正演;最后联合实测数据与组合优化算法,实现随施工推进的参数快速反演与变形预测。结果表明:所建代理模型能合理映射高维土体参数与施工响应的非线性关系;预测精度随监测数据累积动态提升,S6~S8施工步的对称平均绝对百分比误差控制在30%以内;代理模型训练与样本获取均于施工前完成,施工期间单施工步反演耗时由13天骤降至50秒内。可见,该方法在兼顾预测精度的同时突破传统方法的计算效率瓶颈,为机械法联络通道施工风险动态管控提供了兼具理论支撑与工程可行性的技术路径。

    Abstract:

    In order to achieve rapid prediction of construction response for metro cross passages with short construction period and high risk, an efficient inversion and prediction method framework integrating stratigraphic variability modeling and surrogate models was used to investigate the construction response of a cross passage of Ningbo Metro Line 3. Because the construction influence range is large and the reliability of stratum parameters is low, three-dimensional finite element inversion considering stratigraphic variability based on monitoring data is necessary. However, traditional fully coupled inversion faces a computational bottleneck. First, a stratigraphic variability model under sparse borehole data was established based on a three-dimensional Markov random field to decouple the computational burden caused by Monte Carlo simulation. Then, key soil mechanical parameters for each construction step and stratum were screened through sensitivity analysis based on a three-dimensional finite element model. Sample databases for each construction step were obtained through batch calculations. Surrogate models were constructed based on extreme gradient boosting and support vector regression to replace the time-consuming finite element forward calculation. Finally, rapid parameter inversion and deformation prediction along with construction progress were realized by combining monitoring data with a combined optimization algorithm. The results show that the established surrogate models can reasonably map the nonlinear relationship between high-dimensional soil parameters and construction responses. The prediction accuracy improves dynamically with the accumulation of monitoring data. The symmetric mean absolute percentage error of construction steps S6~S8 is controlled within 30%. The training of surrogate models and sample acquisition are completed before construction. The inversion time of a single construction step during construction is reduced from 13 days to less than 50 seconds. It is concluded that the proposed method breaks through the computational efficiency bottleneck of traditional methods while maintaining prediction accuracy. It provides a technical path with both theoretical support and engineering feasibility for dynamic risk management of mechanically excavated metro cross passages.

    参考文献
    相似文献
    引证文献
引用本文

商翔宇,王浩然,韩业顺,等. 考虑地层变异的地铁联络通道施工响应高效反演与预测方法[J]. 科学技术与工程, , ():

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2026-06-24
  • 最后修改日期:2026-10-08
  • 录用日期:2026-10-26
  • 在线发布日期:
  • 出版日期:
×
关于《科学技术与工程》全新官方网站正式上线的通知公告
关于抵制伪造参考文献学术不端行为的声明
关于规范使用生成式人工智能的声明
亟待确认版面费归属稿件,敬请作者关注